Planning a kitchen around how you cook and store
The layout decides whether a kitchen works. Cabinet colour and handles can be changed later; where the sink and oven sit cannot.
Kitchens have changed more than any other room in the last fifty years. The closed-off galley has given way to an open room where cooking and eating happen together, and most of the kitchen renovations we build make that change in an existing house. That often means a wall coming out, a window moving, power and water going to new places, and a floor made level before any cabinetry goes on it. The joinery is the part everyone sees; the building work underneath decides whether the doors line up and the benchtop sits flat.
This page covers layouts, cabinetry, benchtops, services and the order of work. For local detail see kitchen renovations in Wellington and new kitchens in Upper Hutt, and for who does what between a kitchen company and a builder, read about working with us as kitchen renovators.
Call Ethan on 022 621 5980

Kitchen layouts and what each one suits
The layout decides whether a kitchen works. Cabinet colour and handles can be changed later; where the sink and oven sit cannot.
Galley and single-wall kitchens
Two parallel runs, or one, in a narrow room. Efficient to cook in and the cheapest to fit, but short on bench space and hard to share. Good task lighting helps it feel less closed in.
L-shaped kitchens
Two runs meeting in a corner, which frees one side of the room for a table. The corner cabinet is the weak point; a blind corner unit or a lazy susan makes that space usable.
U-shaped kitchens
Three runs and the most bench and storage for the floor area, best in a room that is roughly square. A U can feel enclosed, so we often shorten one leg into a peninsula.
Island and open-plan kitchens
An island needs about a metre of clear floor on every side, so it suits a room that has been opened into the living area. It usually means moving a sink or hob.
Storage, the work triangle and the small things
Cabinetry and benchtops: the main choices
Flat-pack cabinetry is the cheapest route and fine for a rental or a tight budget, but the carcasses come in standard sizes and the room has to fit them. Custom joinery is made to the room, with cabinets sized to the wall and heights set for the people who cook there. Refacing, where the carcasses stay and only doors and benchtops change, suits a kitchen whose layout already works.
Benchtops are a trade-off between cost, look and care. Laminate is affordable. Engineered stone resists stains and is cut and polished by the fabricator off site under WorkSafe's controls for silica dust. Solid timber is warm but needs oiling, and stainless steel shrugs off heat.
Power, water, light and the rangehood
A modern kitchen draws more power than the one it replaces. An induction hob, a wall oven, a dishwasher and a microwave often need new dedicated circuits, which is a registered electrician's job and usually means work at the switchboard. Lighting works best in layers: downlights for the room, strip lighting under the wall cabinets for the bench, and a pendant over an island.
Moving the sink moves the drainage and may need a building consent. The rangehood is not decoration: clause G4 of the Building Code requires cooking moisture and fumes to be removed, and building.govt.nz explains the G4 ventilation requirements. We duct rangehoods outside rather than recirculating them.
The order of work and what sets the timeframe
Cabinetry is ordered first because it has the longest lead time. On site, the sequence is strip-out, any structural change such as a wall removal with its engineered beam, plumbing and electrical rough-in, linings and painting, cabinet installation, the benchtop template and fit a week or so later, and finally the plumber and electrician back for fit-off. A kitchen in the same footprint is typically two to four weeks on site; opening a wall adds time and consent.
What moves the cost most is the cabinetry and benchtop choice, then appliances, then whether plumbing or power moves, then any structural work. Our quote separates those lines so you can see where the money goes.
Contact us about kitchen renovations
Send a photo of the current kitchen, a rough sketch if you have one and your address through the contact page, or call Ethan on 022 621 5980. Email works too: ethan@westbeachconstruction.co.nz. We are available Monday to Friday, 7:30am to 5pm, and we will measure the room, talk through the layout and send a written quote that itemises the building work and the joinery separately.
If the kitchen is part of opening up the house, see our pages on home renovations and home extensions in Wellington. Our guide to designing a modern kitchen for lifestyle and resale value goes further into the design choices.
FAQS
Frequently Asked Questions
In the same footprint, two to four weeks on site once the cabinetry has arrived. Removing a wall, moving the sink or waiting on a benchtop template adds time. The cabinetry lead time before work starts is often longer than the time on site, so order early.
Not for new cabinetry in the same layout with the sink staying put. Removing a load-bearing wall, moving the sink and its drainage, or changing a window usually needs a building consent, and a structural wall needs an engineered beam. We check with your council first.
Yes, if the carcasses are sound and the layout works. New doors, handles and a benchtop can make a solid older kitchen look new for far less than a full replacement. We will tell you honestly if the carcasses are not worth keeping.
Yes. Cabinet sizes, power circuits, gas or induction, the rangehood duct and the fridge alcove all depend on the appliances, so choosing them first avoids a cabinet being rebuilt. We ask for the model numbers before the joinery is measured.
Most households set up a temporary kitchen in another room with the fridge, a microwave and a jug. We tell you exactly which days the water and power to the kitchen will be off, usually only around the strip-out and the final fit-off.
Upper Hutt, Lower Hutt, Wellington city, Porirua and the Kapiti Coast, from our base at Timberlea in Upper Hutt. Travel is part of the quote, and we schedule jobs further away in consecutive days so the kitchen is back in use sooner.
Ready to talk about your project? West Beach Construction is here to help.
See what our clients say about our service
Start with the layout, not the colour
Tell us how you cook, who uses the kitchen and what annoys you about the current one. We will visit, measure and come back with a layout and an itemised quote.